I am putting together a project schedule and I am about to shoot myself.  Is there any way I can set up a project to track both duration and effort.  Basically, I want to show task that may take 2 weeks to complete, but might only be 8 hours of effort.  Other than adding resources and making them a %, I cannot figure out a way.  I do not want to do the resource %, because we want to see how much effort we need first.  In addition, I want to track what % the task is complete by both duration and effort.  For example, the 8 hour task that takes 2 weeks to complete.  If I put in that we have spent 8 hours on the task, then project automatically puts the task 100% complete, but we may only be 75% complete.  
I want to be able to show this...
task start on 5/1 and goes through 5/12 (10 working days). The task is going to take 8 hours to complete. On 5/8, I want to show that we have spent 10 hours working on the task, but we are only 50% with the work.
If anyone can show me how to track both of these, I would greatly appreciate it.
Thanks!
	
		
			
		
		
	
			
			I want to be able to show this...
task start on 5/1 and goes through 5/12 (10 working days). The task is going to take 8 hours to complete. On 5/8, I want to show that we have spent 10 hours working on the task, but we are only 50% with the work.
If anyone can show me how to track both of these, I would greatly appreciate it.
Thanks!
 
				
		 
 
		 
 
		
 
 